Historical Timeline

September 1896

Grand Haven electric utility is created – Grand Haven’s electric utility was created on September 29, 1896, when citizens voted to approve a $10,000 bond for the first municipal electrical generator.

1911

Net book Value – The utility was appraised at a net book value of $25,244.33. Additional equipment was added as needed.

1915

Steam engine replaced – The original steam engine is replaced by a 500kw turbine and other additions are made.

1917

Turbine & Boiler – A 1000 kw turbine and boiler are installed.

1924

NEW Boiler Room – Work begins on construction of a new boiler and the addition of a new 1500 kw turbine. Total cost $110,356.

1927

System Upgrades – Additional equipment is installed, consisting of a 500-hp boiler and stoker, a Zeolite water softening system, boiler feed pumps, and a complete coal conveying system at a cost of $54,589.

1929

Construction of a Diesel Generator Plant – In response to system growth, the City begins constructing a diesel generator plant. Work was suspended temporarily in early 1930 when Consumers Power Company offers $1,200,000 for the system. The offer was turned down and a Board of Public Works was created during the same election.

Inside Photo

Building Photo

 

1930

Construction resumes on Diesel Plant – Construction of the diesel plant resumes after April 1930 election. Two 1150-hp DeLaVergne 6-cylinder engines connected to 800kw Elliot generators with direct connect exciters are purchased and installed. Project cost $217,000.

Building Photo

1934

DeLaVergne Diesel Engine – A third identical DeLaVergne diesel engine is installed at a cost of $82,000.

1937

Nordberg Engine Installed – In an effort to stay ahead of load growth, the diesel plant is expanded, and a fourth engine is installed, a 2250-hp Nordberg engine. The purchase is financed in part by a WPA federal government loan. Cost $200,000, water intake pump house $19,000.

Annual Report 1937

1938

Fourth consecutive rate reduction – The utility implements the first of four consecutive annual rate reductions.

Annual Report 1938

1939

FREE Month of Electricity “PAID” – The utility again reduces its electric rates, this time retroactively, and gives all customers a free month of electricity by marking all April 15 thru May 15 electric bills “PAID”

1940

Nordberg #2 Engine Installed – Continued load growth requires a fifth diesel engine. The Nordberg #2 engine with 3850-hp was installed.

Annual Report 1940

1941

Annual Report 1941

1942

Annual Report 1942

1943

Annual Report 1943

1944

Annual Report 1944

1945

1945 Annual Report

 

1946

1946 Annual Report

1947

1947 Annual Report

Board of Public Works, Grand Haven, MI – 51st Year

1948

Nordberg #6 Engine is installed similar in size to Engine #5.

Read Article

1950

Largest municipal diesel plant in the U.S. – A nine-cylinder Nordberg diesel (engine #7) is installed, at that time one of the LARGEST diesel engines built in the United States. With the addition of this engine, BLP is the largest municipal diesel plant in the U.S.

Tribune Photo

1952

Generating capability of 16,430 kilowatts – The Grand Haven Diesel Plant has a combined generating capability of 16,430 kilowatts produced by engines totaling 23,170 horsepower.

1954

$1.5 million  3-year expansion – The utility completes a $1.5 million 3-year expansion project that boosts the plant’s horsepower to more than 26,000, replacing the aging 1934 DeLaVergne engine #5 with a ten-cylinder Nordberg.

Inside Expansion Photo

Engine Photo

1959

Construction begins on SIMS Generating Station Units I & II – Identical coal-fired high pressure condensing units capable of producing 10MW each installed on Harbor Island. Designed by Lutz & May, built by Elzinga & Volkers. Cost $4.95 million, completed in 1961.

Construction Photo

Construction Photo 2

Construction Photo 3

 

1960

Construction of SIMS Generating Station Unit I & II, built by Elzinga & Volkers, construction finished in 1961.

 

1961

Grand Haven Municipal Power Plant Report

Aerial Photo of Sims

Power Pool Interconnection on island

Linemen at Work

 

1962

Charlie Allen in the control room

Gerald (Tiny) Dykhuis

Inside Sims with a Northern Crane above the control room

 

1976

Grand Haven Power Plant to be Renamed – J.B. Sims Generating Station

1980

Construction begins on SIMS Unit III – Construction begins on SIMS Generating Station, Unit III, a 65 MW
coal-fired power plant. The plant and its environmental protection equipment cost $88.5 million. The commercial operation was achieved in 1983. Unit is the first in the nation to sell gypsum byproducts.

Detailed Brochure

1980

1980 Annual Report

1982

Annual Report 1982

1986

SIMS Unit I & II Retired – SIMS Unit I & II are retired from service due to economic and environmental issues.

Pictured (Left to Right) – Roger Easton, Bob Atkin, Glen Eaton, Emery Holzinger, and John Montgomery.

1988

Public Power Week Tribune Insert October 9-15, 1988

2004

Low Nox Burners Installed – SIMS Unit III installed second-generation low Nox burners from Advanced Burner Technologies reducing emissions by 50%.

2006

SIMS Unit III Upgraded – SIMS Unit III boiler, turbine, and auxiliaries upgraded from a nominal 65 MW generator capacity to 80MW.

2008

Board approves purchase power commitment w/MPPA for up to 4 MW landfill Gas.

2009

Installed Selective Non-Catalytic Reduction (SNCR) – Sims Unit III selective non-catalytic reduction (SNCR) installed for an additional 30% reduction in Nox.

2013

Board approves purchase power commitment with MPPA for 2.4 MW Wind Generation.

May 2016

May 19, 2016 – 20 Year Purchase Power Commitment with MPPA for Huron Wind Project for 9.67% of our renewables.

August 2016

August 25, 2016, Board approves construction to remodel Service Center.

Construction Photo

October 2016

October 4, 2016, Community Mortgage Burning Celebration held at Sims site.

August 2017

August 17, 2017, Board approves purchase power commitment with MPPA for Pegasus Wind Project (replaces Huron) for 6% of our renewables.

September 2017

September 2017 Service Center Remodel project complete.

September 2017

September 28, 2017, Phase I of the BLP’s transmission system upgrade project was complete and under budget.

July 2018

July 27, 2018, Phase II of the GHBLP’s transmission line project is complete, which includes both the transmission and distribution portions of the project.

September 2018

September 20, 2018, The Board of Light & Power approves a 20-year Purchase Power Commitment with Michigan Public Power Agency for approximately 10 MWs of energy from the Assembly Solar & Energy facility

November 2018

November 11, 2018, last shipment of coal was delivered to JB Sims.

March – May 2019

March 21, 2019 – Board approves transition to NITS (Network Integration Transmission Service) on June 1, 2020.

May 16, 2019, Board approves MPPA 3-year Capacity purchase from June 1, 2020, till May 1, 2023, to comply with Michigan PA341.

May 19, 2019 – Board approves Purchase Power Commitment with MPPA for additional solar to replace Pegasus Wind Project.

 

June 2019

June 18, 2019, Phase III of the GHBLP’s transmission line project is complete.  This phase concludes a three-year project that encompassed a complete rebuild of the GHBLP owned transmission system from Robbins Road in Grand Haven north to Sternberg Road in Fruitport Township.  This transmission system rebuild is sized and designed to supply the Grand Haven area community with safe and reliable electric power for many years.

November – December 2019

November 2019 – Board approves letter of authorization with MPPA for 15-year capacity purchase for up to 8 MWs.

December 2019 – Board approves AMI contract for purchase and installation of AMI (Advanced Meter Infrastructure) equipment for a total cost of $2.3 million.

December 19, 2019, Sims’s demolition contract with Bierlein Company is approved in the amount of $5,053,333 million.

January 2020

January 16, 2020, Board approves Island Substation rebuild for a cost of $4 million.

February 2020

February 13, 2020, J.B. Sims Generating Station burned through its final pile of coal. The BLP is successfully progressing through its Strategic Plan objective to transition from primarily one fuel source to a more sustainable, economical, and diversified power supply portfolio for the community.

February 2020

February 20, 2020, Board approves Progressive AE to design an interim snowmelt system.

Snowmelt system

April 2020

April 2020 Due to COVID 19 Pandemic, April 2020 was the worst sales record month in the last 20 years.

June 2020

June 1, 2020, Sims Unit III and Diesel Plant retired. Utility moves to NITS (Network Integration Transmission Service).

June 2020

June 18, 2020 Board approve Notice of Intent for Bond Resolution and First Supplemental Revenue Bond Resolutions.

November 6, 2020, Board-approved contracts to develop detailed design and engineering plans for an operations and technology center at the utility’s Harbor Island location. The redeveloped site would house GHBLP’s advanced distribution hub, operations staff, grid interconnection, downtown substation, and a 12.5MW combined heat and power generation facility.

November 2020

November 5, 2020, New Island Substation is brought online.

February 2021

February 12, 2021, Implosion of the Sims Scrubber Building.

Scrubber Implosion Video

February 2021

February 19, 2021 Implosion of JB Sims stack and Unit III Boiler.

Implosion Video

August 2021

August 2021, Board approves 5 yr. capacity purchase for approximately 15 MWs and cancels proposed 12.5 MW RICE plant project.

September 2021

125th Anniversary 

December 2021

$25 million in bonds were sold to fund demolishing the Sims power plant, conducting environmental remediation, rebuild the Harbor Island substation, and implement advanced metering infrastructure (AMI).

July 2022

The Board authorizes a $2 million contribution to the MERS Defined Benefit Plan as part of a five-year strategy to reach 100% funding.

 

March 2023

The Board approves a 10-year Power Purchase Commitment (PPC) with Michigan Public Power Agency (MPPA) for the BLP’s pro-rata share of MPPA’s Battery Energy Storage Systems Capacity Purchase and Sale Agreement with White Ox LLC.

May 2023

The Board restricts reserve funds for the purpose of covering its liabilities for environmental remediation of the Sims site.